![]() |
| P |
|
|
| |||||||||||||||||||||
|
Work Party at Honing Staithe Cut.Sunday 13th December 2009.THE PLAN. To remove the fallen tree at bridge end of cut; to reduce the overgrowth where possible; to further back-fill the walk through the wood with brash; generally tidy up; identify trees which might present a hazard.
WORK ACHIEVEMENT. The day started off with a rain-shower and this state of affairs continued with intermittent sunshine.
The first item on the agenda was to remove the fallen tree which was understood to be from 'land owned by others' and the brash etc replaced onto that land. Other fallen branches etc were also removed.
The walk on the north side of the arm was widened a little with the use of strimmers. I set off with Tim to walk the Walk and identify possible hazardous trees. This was done and seven (7) trees identified which will be reported to the land agent for further inspection. Roger and Peter, meantime, were filling in more brash to the walk through the woods. This walk is certainly quite 'damp' in places but the brash is making it a little more bearable.
Not being able to leave the vehicles parked there without attendance it was decided to call it a day, well, after the much looked forward to piece of cake and we left just after 14.00.
My thanks go to all who took part in the morning and you DID make a really beneficial difference to the scene. |
|
|
Work Party at Briggate Mill PondSunday 29th November 2009.The Plan. Within this and the next two work parties at this site and before the beginning of April next, to complete the clearance of the mill pond site; outline the banking to the pre-laid out marker posts; to clear the roadside pond wall in order to ascertain the extent of repair/rebuild work required; to reduce vegetation growth on the chamber island; to remove old tree roots from the pond base; to check for clay puddling in pond basin; ascertain and complete work of clearance at western end as far as possible. Work Achievement. The weather started with high cloud but as soon as the party was on site the rain started and developed into a stair-rod 'drizzle'. Notwithstanding this the party carried on and after about an hour of water-cooled working, the precipitation ceased and before lunch-break, the sun broke out and continued until close of play. With a total of thirteen (13) folk on site at various times it showed the keenness to complete this project.
After H&S and task briefing, we rapidly set to! Tom and Digger were present and launched themselves at clearing the old tree roots, deeply embedded in the base, which was successfully carried out to over 70% of the area, the worst parts. In the main area of the mill pond, there is only one small tree left to be removed - apart from the large trees growing under the roadway and in the western end area. Strimmers were used to start the clearance on the chamber island and in particular to reveal the locations of major obstructions e.g. metal posts retaining the chains used to secure one of the lower lock gates in a vertical position. Marc used the Big Machine to clear the rest of the island in short time. Strimmers and a reed cutter were employed near to the wall and spill basin to great effect. We ceased labours at about 15.00 and left the site in a much changed state. A few robins were noted as we worked, very grateful for overturned earth and exposed worms. One gentleman, who stopped by, expressed his great pleasure at the thought of the restoration of the pond as he had learned to swim there as a lad! A tremendous effort was made by all and that shows in the results. I am confident that the other two work-parties here will finish the planned task and leave the site a pleasure for both local folk and visitors alike. We plan also to return during the summer months to cut the grass (?) on an (ir)-regular basis to keep it looking decent and tidy. My thanks go to everyone who attended with such enthusiasm! The further two visits here were planned for March 2010 but this may have to be changed to February - watch this space for confirmation. The next work-party will be at Honing Staithe Cut on December 13th - the last outing of 2009. |
|
|
Work Party at The Old Wherry PH , Royston (Austin) BridgeSunday 15th November 2009.Here follows the report as sent to me by Chris Black, Leader on the day.
"The day started badly at home! Because the weather had been so poor on Saturday with strong winds and heavy rains my usual job of loading the car with tools, mowers and all the other requisites for a work party was postponed until Sunday morning. Our weather forecasters with their £30m computer had promised a fine start but it was raining solidly. I got wet but as we set off the sun duly appeared and it remained fine and warm for the rest of the day. "We then concentrated on clearing the canal bank on the west (house side). Matt cleared much of the sedge growth with the large strimmer and we soon had all the bushes and old tree stumps removed. The bank slopes at about 45 deg and efforts to find a retaining wall failed. An old picture of the moorings confirming that it was likely to be a wooden structure. "We gradually worked our way north to the bridge. Trees were removed from the east bank and stacked there. Brash and bushes were cut down together with brambles and sedge making the whole area look very tidy. It would seem that the brash above the bridge had been cut down by Highways and we cleared up their mess! As pointed out by David R we did not cut down the bushes between the house and the bridge for security reasons and having cut back bushes below these installed a temporary chain link fence to deny unauthorized access to the house. This arrangement will need to be altered at a future visit. "We had a visit from Laurie Ashton and his mate to see how things were progressing. He was very pleased with our activities. We discussed the removal of the remaining larger trees which he agreed would have to be taken out to gain access for any dredging / re-profiling. The banks have dropped in places and require building up again.
"We were visited by friends of Mrs. Harvey, the first two thought we were going to be there last week and seemed concerned that we were upsetting the wildlife which I hope I managed to convince them otherwise. The other two people came to feed the cat and were very interested in our canal restoration. They knew Roger H. We were shown a large cast iron plate about 2' round which had written on it - North Walsham Canal Co Bridge, 5 Ton axle weight limit. It would make a fine addition to our finds collection! My grateful thanks go to Chris for sending me this report after a hard days' slog and also, of course, to the many members of The 'A' Team for applying themselves once more to the effort. The next meeting will be at Briggate on Sunday 29th November 2009 when a fuller explanation of the works to be completed there in the short term., will be given. |
|
|
Work Party at EbridgeSunday 25 October 2009.
THE PLAN. To continue removing trees and other bush growth from the canal bed and lower bank on the eastern side of the canal upstream of the lock. To reach the 'target', which is the point where no more trees have fallen into or are blocking the canal or lower parts of the bank.
WORK ACHIEVEMENT. The weather was mainly clear with blue skies and a little breeze at times, sometimes a bit stronger from generally the south west. No rain at all.
When the first members arrived there, it was to find that an enormous number of trees and saplings had been brought down since our last work party here. We had expected some work to have been done, but this was just amazing! My thanks go to whom so-ever co-operated in this manner. 'All' it needed now was for the debris to be cleared away to a safe and tidy location - and this was done to a large area during the day.
On arriving back at the main party, I stated that the target had been reached and asked casually if anyone could guess how far that would be from where we stood? Chris correctly guessed the answer to be 100yards (what else?) and as a reward, and also to ease the many aching backs, I blew the whistle for the lunch break. After the cake the Team staggered once more onto aching legs and set off back to the work face, with Carole in charge. Chris and I set off for Honing and found a very pleasant sight awaiting us. The water level was fairly high for this area and the canal fully covered its allotted space between the banks. Even the Staithe Cut was replete with water and no land protruding from it. We duly cut the grass, which was not a hard task, and strimmed the sides of the walk as far as the new bridge, which tested to be really firm in it's' location. It is noted that a tree, near to the road bridge, has collapsed onto the walk way and will need to be removed. It was not ascertained as to the ownership of said tree, but it could be from the land under the control of the County Highways Department. On returning to Ebridge we found that the Team had ceased work (it was getting on) and we departed at about 16.15 following what can only be described as a very good and successful day. Some of the brash was left in piles on the dry canal bed for future disposal. My grateful thanks to all who came and worked so very hard in making a big impression.
The next outing is to the Bacton Wood area and following talking with the lovely lady owner of the Wherry Inn, Royston Bridge on the Bacton Road, B1150 we shall be at the Wherry Inn site to work on the canal in front of the Inn on Sunday 15th November 09. Therefore please go directly to the site and not to Bacton Wood Lock.
![]() "Rescueing Damsel in Distress!"
![]() "Before."
![]() "The Task."
![]() "After." |
|
|
Work Party at EbridgeSunday 11 October 2009.THE PLAN. To continue to clear trees and bushes from the canal bed and bank on the north-eastern side upstream of the lock. Two people to cut the grass at Honing Staithe Cut. WORK ACHIEVEMENT. The weather was forecast to be generally good with maybe the odd shower - it turned out to be generally fine! With a total of seven members of The Team on site, plus guard dog, we attempted the impossible - to clear the final, now famous 'one hundred yards' to the end of the tree line.
At the start, our new member, Matt, wielded the strimmer through the overgrown weeds and grass on the chamber island with deadly accuracy and finished off the beheading with the mower! Not the entire island, you understand, as that was not a major requirement for this day. Sufficient to be able to park one vehicle and trailer - and a place to enjoy our lunch break. Carol apologised for not making a cake but had made a large Norfolk Scone instead. How nice and thoughtful! One person who shall be nameless, and probably outcast? said, on seeing the scone that it made him think of coping stones! How cruel?
During my little 'talk' I mentioned that whilst all the work carried out by The Team was very important indeed, there was a great deal to be done behind the scenes.
After the scone and that 'loaded down feeling' we all returned to the task on hand and continued until about 15.15. Mr Laurie Ashton paid a visit and discussed various ways of moving forward, including making the banks watertight. The result of the outlet of the culvert from Mr Paul Gibbons' farm dyke, which runs under the canal, could be seen in the backsoke, which is now fairly heavily restricted with weeds again.
![]() Clearances achieved this day. Owing to running out of time, the planned grass cutting at Honing Staithe Cut did not take place and will now be done during our next meeting. My thanks again go to The Team for another excellent days work with the resultant new views of the mill from a distance! ![]() David Revill, work party organiser, walking back from exploring the next length to be cleared on October 25th 2009. Our next meeting is again at Ebridge on 25th October 09. |
|
|
Work Party at Honing Lock.Sunday September 13 2009THE PLAN. General clearance around the lock and to investigate the use of the backsoke as a way to a portage point; clear this if possible WORK ACHIEVEMENT. As I could not have been present due to vacation, I had left Carole B in charge and this is her report:-
The weather was overcast and very windy with a little rain in the afternoon - but insufficient to require a cessation of work! Two areas were tackled
Both areas were so overgrown that it appeared as if we had never been there before! Considering that there were only four of us volunteers present, plus guard-dog, the amount of work achieved was superb. It was also nice to see Laurie Ashton, who came and had a chat. He is looking forward to meeting with the next work party at Bacton Wood at the end of the month. The H&S was carried out at the beginning of the day and the attendance form was duly signed by the four people present. Rock cakes were distributed among the needy (i.e. 'the workers') at the lunch break. We called it a day at about 15.30 and departed feeling quite pleased with the days' endeavours. An idea was put forward by Graham, that a little sign post giving the details of the Trust could be erected near to Honing Lock in order to inform the many people who wander in this region, and who may yet even wish to become members of the Trust.
My thanks go to Carole for taking on this days' burdens and for the above report! I shall report the idea of an information post back to the Trust and thank Graham for the thought. My grateful thanks also go to the three stalwarts who assisted in the work party. |
|
|
Work Party at Briggate Mill Pond.Sunday 16th August 2009THE PLAN. This is a changed venue with the additional task of visiting Bacton Wood Mill Lock. Basic plan at Briggate is to clear as much as possible of the brash previously stacked and to continue clearance of pond area.
WORK ACHIEVEMENT. Weather good for the duration of the work on both sites with a slightly cooling breeze, which also helped immensely with the burning of the brash.
![]() Bacton Wood. On the east side, brick work could not continue until the condition of the paddle chamber had been established. We found that there was a considerable amount of rubble blocking the chamber and culvert and this was removed - amounting to about ½ a dumper truck full! This done and the state of the chamber and culvert confirmed to be sound, we took tea and returned to Briggate. ___
![]() Briggate.
Of the total of eight on site, I had left Jane, The Administrator, with two impressions made by an artist, of the Mill Pond as it is hoped to appear when completed. One local lady came to the site and asked to speak with me but Roger, in my absence, helped her with her enquiries. My thanks go to the whole of the Team present, for achieving such a great step forward at Briggate, without which, the next step would have been delayed.
As previously stated the work party originally planned for Sunday 30 August is cancelled. This means that the next site work will take place on Sunday 13 September at Honing Lock (NOT Staithe Cut!). The work party at the end of September will also be at Honing Lock, on the 27th.
|
|
|
Work Party at Bacton Wood.Sunday 26th July 2009THE PLAN. To discuss with Mr L Ashton the best way forward in clearance of bricks, rubble, timber and plant growth at the lock; to inspect the breach up-canal of the lock.
WORK ACHIEVEMENT. Weather was overcast all day with some sunshine - quite pleasant working conditions! In the meantime, more capping bricks, and others were removed from one of the chamber walls and cleaned. Some more raking out was done on the cheek walls and also a large area of pointing carried out. At the tail end of the lock, work carried on with clearing the weed and other growth from the walls and it is left with both ends of the tail walls now exposed. A couple of trees were removed from this area, one from each side and the view from downstream is now very favourable - with a clear sight now of what is to be done and a dream of what it should eventually look like!
Meantime, I walked up-canal with Graham to inspect the site of the breach and talk about what could be done at this point to restore the water to the canal and leave the flow of the present water along the backsoke unimpeded. With the use of the grab machinery, more silt and rubbish were removed from the chamber of the lock. The floor of the chamber is reputedly covered with brickwork, but this could not be verified at this stage.
Now that all these tasks have been completed, it is down to the construction folk to carry on with their work to make the mouth of the lock watertight once more. We will be required on site again, by which time, scaffolding will have been erected and we can commence on the removal of the outer skin of the chamber walls, brick by brick, prior to reconstruction of the remainder of the structure. Of interest, the now dried out pieces of the old gates and structures were viewed, showing the methodology of construction from nearly two hundred years ago. |
|
|
Work Party at Briggate Mill Pond.Sunday 14th June 2009THE PLAN. To work westwards from the centre, on the road side of the pond. To clear 'base camps' on FP19 upstream of Bacton Wood Lock
WORK ACHIEVEMENT. Weather was as planned to be fine all day and so it was, with working conditions very pleasant. In order to carry out a check on the difference in the wild life numbers/types between the extensive survey carried out in the mid 90s' and today, I had prepared a survey sheet, which was to be put to any people who cared to stop and talk with us, indicating what had been seen and when. We have certainly not observed any wildlife, nor trace of, other than birds and the odd frog, in the area on any of our visits to this site. Shortly after the lunch break, our two members returned from a very successful visit to Bacton Wood and joined us in our chores. Whilst a goodly amount of timer was removed to storage piles, which is a ponderous job, there is still a great amount of fallen timber to be removed from the corner of the pond site. The standing trees in the pond containment wall will present quite a problem. The roots of all such trees can be seen to be growing under the roadway and apparently none going into the pond bed. Should a tree fall over due to storm (or other) reasons, it is likely to rip the roadway apart. However, the question arises as to who holds the responsibility for such trees? Before the wall can be pulled apart and afterwards rebuilt, the trees will certainly need to be removed. As it is considered that the sad condition of the wall is largely, if not wholly, due to the Norfolk County Highways Authority, (viz my survey and report dated 27th July 2008), there will most certainly be a long wait for any answers! As the weeds and some grass growing on the chamber island were left standing, it was not possible to take better measurements to ascertain the quantity of rebuilding material required to re-instate the former natural and level areas of the island. The piles of brash, which we had created earlier, were left untouched due to possible bird habitation at this time of the year. All in all, a successful day for what could be done and my thanks go to all the nine of you who attended and as usual applied yourselves to the tasks in hand. We are winning, for the benefit of nature, local people and visitors alike.
NOTE. Roger Hopkinson, Chairman of the Canal Trust, has managed to arrange for the site at Honing Staithe Cut to be inspected for a possible award in July. |
|
|
Work Party at Bacton Wood Mill Lock.Sunday 31st May 2009.
THE PLAN. To liaise with Mr Laurie Ashton and make on-site decision as to work to be carried out - probably removing bricks from lock walls, as I had made a site visit two days before.
WORK ACHIEVEMENT. The weather forecast was for wall-to-wall sunshine and so it turned out to be! During the H&S bit, the requirement was issued that hard hats would be worn when working at low levels beside the walls. We split into two groups and launched ourselves at both the cheek walls at the mouth to the lock, which is of course, still dry. The cheek wall, nearer to the mill, had already recently been rebuilt from the upstream end to as far as the paddle chamber reveal, and a start had been made on its' partner opposite. ![]()
The task today, was to remove bricks from the surface and behind, back as far as solid foundations. Full clean bricks only were to be saved for further use, with halves etc put into the dumper truck and removed. The Team on the mill side wall removed a great deal and exposed the paddle chamber, which discovered that there is a lot of metal strips, bricks and concrete (and probably other rubble) in the base of the chamber - this to be investigated at a later date.
After lunch taken in the very welcome shade of some nearby trees - and a cup of tea offered in the mill by Julie and Laurie, we continued the task. The paddle winding gear on the opposite side was removed by mechanical means and cemented-on bricks cleared from it. The work carried out today is the first we have done with a direct and almost immediate result in the line of reconstruction. We have left the site with probably some three to four weeks work to be done by the bricklayer, John. All together, a very pleasant day with very encouraging results - a real booster for The Team and I thank all of you who attended for your joint efforts.
The next meeting will be at Briggate Mill Pond site on Sunday 14th June 09 and at Ebridge on Sunday 28th June 09. The programme for the rest of the year will be published shortly. |
|
|
Work Party at Honing Cut and Walk.Sunday May 10th 2009.
THE PLAN. To tidy any growth around the Staithe Cut and to prepare the walk path through the wood for elevating above the boggy level of the terrain. As I was not to be there, Mr Chris Black would be Leader. WORK ACHIEVEMENT. The following report is as sent to me by Chris:-
Report on activities at Honing Staithe Cut on 10th May 2009.
We mowed and strimmed the area to the road side of the staithe which has started to grow quite profusely then moved our kit to the far end of the walk.
This time we had two wheelbarrows but it was difficult to find the dry soil so we didn't progress very quickly at first however a chance bit of deeper digging near the large tree at the top part of the track revealed sand and gravel which I think is natural! We need to explore this at a later date as it would be very useful on other parts of the track. The 'hump' near the top of the track was removed which turned out to be dumped sandy soil. Chris Black
Many thanks for that report, Chris and to Marc and Carole for also being there. |
|
|
Work Party at Honing LockSunday April 26th 2009.
THE PLAN. To check on the state of growth of the natural habitants at the site and trim if possible; to ascertain the extent of the fencing, which had been erected by the Canal Company since our last visit here; to check on the viability of portage points at both ends of the lock. WORK ACHIEVEMENT. Weather was booked to be first class all day and so it was with just a few clouds making a passing appearance at odd times; quite warm and very pleasant. With the H&S pleasantries behind us, the plan was explained and we took off to our various tasks. The grass besides the new fencing alongside the Public Footpath was trimmed to look very neat and tidy and then a concrete obstruction was stumbled over near to the mouth of the lock on the western side. This obstruction was covered in bramble and had a sapling growing out through it, albeit the top has been lopped some time ago.
We made welcome to a new attendee, friend of Graham by the name of John - again welcome John and thanks for your enthusiastic efforts at this visit - look forward to meeting you again soon. A pair of canoes arrived at the tail of the lock during the morning in spite of a fallen tree across the canal downstream near to the first bend. The occupants declined the offer made by Chris to continue their journey upstream of the lock. We had luck later however, when a family arrived in two canoes and I encouraged them to try the newly cleared (?) canal to Honing Staithe Cut
We took lunch on the freshly cleared return wall and watched as the two canoes were transported past us and re-launched. The party later said that the canal was a pleasure and that they had even seen tadpoles and fish fry in the Staithe Cut! The approach bridge over the back soke between Honing Lock Road and the lock has suffered two broken pieces of wood on the decking and the main handrail (upstream) support post on the far side of the bridge of the mouth of the lock is badly rotten - these two points will be reported to the proper authority. Once again, Team, thank you for attending and providing such a good result with the added benefit of once more seeing the canal used again after many years. I am sure that now that the trail is open, we shall see more use of this lovely piece of natures' beauty.
One small piece of admin! You may recall that when I took over as Leader, Roger Hopkinson and Marc Lines were also appointed to assist me. Well, owing to the added pressures of subsequently being elected as chairman of the Canal Trust, Roger has stepped down as my assistant and Chris Black has taken his place. The next work party will be at Honing Staithe Cut on Sunday 10th May 09 when Chris will be your host as I shall be away. |
|
|
Work Party at Bacton Wood Lock.Sunday April 5th 2009.
THE PLAN. To liaise with Mr L Ashton and discuss requirements for the day. WORK ACHIEVEMENT. Weather sunny and warm. This is the second work party in seven days, which is very unusual of course, and six members of the Team turned out. Apologies had been received from four regulars. The basic project was to clear as much of the natural overgrowth as we could from the lock structure. With this greenery removed it will be easier for the mechanical components of the Team to demolish those parts that need to be removed prior to rebuilding of the total structure. ![]()
Our David, the long range visitor from up north, applied his undoubted skills to ridding the bank, at the tail of the lock, of all saplings and small trees and bushes. The other undergrowth did not fare well either under his onslaught. Well, he was assisted by the more muscular Graham for part of the time! I needed to leave early owing to a prior engagement and left the Team in the capable care of Chris Black. My thanks go to all of the Team and look forward to seeing you at Honing Lock, after a three weeks 'holiday', on Sunday 26th April. |
|
|
Work Party at Honing Staithe Cut and Canal.Sunday March 29, 2009.
THE PLAN. To continue to clear canal and side, between D Bridge and the lock; dredge Staithe Cut and entrance thereto. WORK ACHIEVEMENT. Weather forecast hoped (I seldom believe forecasters!) for wall-to-wall sunshine! Fact - on waking up it was just so but on arrival at site, the 'sunshine' was falling as hail and sleet! Never mind though, as the rest of the day was very passable.
Twelve people turned up including two new members to the Team, Wendy and Dick, who were made welcome and duly instructed in the ways of the world! After the usual H&S, the Team was briefed on the plans for the day. ![]()
By the end of the period, the Cut was made to look very presentable with the bank on the road side looking very pristine, although black, and with deeper water along it's' side. The deep gulley near to the canal bridge was also filled in and levelled with the spoil.
Whilst this was progressing, the remainder of the Team ambled over to the south side of the canal proper between the D Bridge and the lock. There we were greeted with a mountain range of brash left over from the working parties last year. As the main purpose at that time was to clear the debris and trees from the canal, dispersal of the brash was not the top priority. ![]() Lunch was taken at the head of the Staithe Cut and the water looked to be in fine shape - which was better than us after Caroles' pieces of cake! The vista along the Cut towards the canal was truly inspiring and we all commented on how much better than this it will look when the summer growth takes place and the trees and bushes become covered in leaves once more. With nature taking advantage of the now cleared site, it was good to see some fry in the water! How did they get there? There were also some clumps of frog spawn, but not toad spawn, floating above the fairly new green weed. A very good days work with inspiring results. But…..there will need to be a couple more visits to this site to truly get it cleared, but the canal along this straight is even now a rewarding sight being clear of overhanging trees and providing free access to canoes through from the lock to the Staithe Cut. My thanks go to all who came along and provided such good results on the ground. The next work party is at Bacton Wood Lock on Sunday 5th April 2009. |
|
|
Work Party at Ebridge Lock and Canal.Sunday 8 March 2009.THE PLAN. To continue the clearance of trees and debris from the side of canal bank and the canal itself to the north of Ebridge lock. WORK ACHIEVEMENT. Weather: a more than pleasant start to the day and really surprising for the time of year with wall-to-wall sunshine and without a cloud in sight. Clouds started to appear just after the lunch break and made themselves felt by 14.25 when they opened up with a strong downpour accompanied by a very strong wind associated with the frontal system.
After the usual start to the day of H&S, came the briefing of the plan. Ten of the dedicated Team turned up to forward the cause! And on such a splendid day it was not really surprising. In short time we all moved into our positions and the debris and fallen trees were quickly being cut, by whatever means and stacked into the extension of the eco-friendly hedge.
The bed is apparently largely of sand. Having made a seemingly effortless advance along the side of the canal, lunch was whistled and we retired to our reed-bed area to rest awhile. The sun shone brightly and warmly down onto us in appreciation of our labours.
"The end in sight."
During a tug-of-war team effort on dragging a tree out of the canal, Carole's' dog got a bit uppity with me until I said to him that he should go for the guys in yellow jackets - which he promptly did, much to everyone's' amusement…except those wearing yellow jackets of course.
On returning to our vehicles, and before reaching the lock chamber, the view over our shoulders made all the hard work of the day worth-while. ![]() This same view cannot, regrettably, be seen from the road bridge because of the height of the encroaching reeds. This is a shame as the view is not available to the general public. Does anyone know of a friendly chap with a handy reed cutter? So again my thanks to the faithful members of The Team for yet another day well spent with a splendid result. The next work-party will be at Honing Staithe Cut for work on the canal side between D Bridge and Honing Lock by kind permission of Mr A Paterson. |
|
|
Work Party at Ebridge Lock and Canal.Sunday 22 February 2009.THE PLAN: To check on the growth of grass etc on the chamber island and to clear trees, debris and brush from canal, upstream of lock, and along the north east bank.
WORK ACHIEVEMENT. Weather. Generally fine but fully overcast; no precipitation but chill breeze at times.
Before the lunch break, considerable progress had been made along the length. Replete and staggering back to the work-face, we all continued in a keen and expectant mood. The timber and brash, both dead and alive, seemed to fly into the continuation of the long established hedge built as a natural habitat for insects and a haven for smaller animals - and hopefully a nesting area for birds - come the time. Just as we were considering our success at leaving a well cleared and tidy stretch, Mr & Mrs L Ashton appeared and were pleased with the scene. Before departing, The Team were informed of the forthcoming evening illustrated talk about the Dilham Canal 1825 - 2025 to be held on 17th March 2009 in the Dilham Village Hall at 19.00 for 19.30 start. It was good to welcome a new member today, one Malcolm B, and to say thank you to all others who turned up and did a great job. I must also here acknowledge the great assistance given to the cause in looking after, bringing to the work parties and in some cases providing, tools. It is not easy to muster so many tools for each meeting but Marc, Carole and Chris do just that. In addition, the tools and machinery are also well maintained. Thank you! The next work party will again be at Ebridge, on Sunday 8th March 2009. |
|
|
Work Party at Briggate Mill Pond.Sunday 8th February 2009.THE PLAN. To burn brash as accumulated over last two work parties; to remove other undergrowth etc to fire; to use digger to dredge as much as possible and start to rebuilding of the banks; to use the digger to remove old tree trunks and roots from pond.
WORK ACHIEVEMENT. Weather: fine and sunny with some very high cloud and just a slight breeze for most of the time! (I knew I could do it again!). The first fire was set on the site of a previous one adjacent to the waters edge. A second was set in the dip and between them, they consumed all of the light brash from the mighty pile on the chamber 'island'. Not only was the result a very pleasing sight, but the potatoes baked within, were really delightful! These, followed by a piece of the inimitable cake….what more could one want? The more stable pieces of timber were taken and laid to form a raft between the two islands for later use by Digger in traversing the soft area. Other similar pieces of timber were laid to form an edge to the island on the planned side of the pond. It was later found that the millpond water was lying at a height above that of the canal! A small channel was dug and the water started to trickle into the canal. Whilst it is the object of the exercise to eventually fill the millpond with water, it is not a welcome sight at this time as it impairs work patterns. We will however prevail and perhaps the water will drain away sufficiently to permit easier access to the other piles of brash by the other bank, on another occasion.
Of the people who stopped to speak with us, three were prospective helpers and not a single local resident made themselves known to us. A pity!
A very successful day spent in good company and weather, with very pleasing results. My grateful thanks go to all of the ten who attended and made this possible. |
|
|